Anglian Water

image
Client name:
Anglian Water

Location:
Kirby Road, Kirby Bedon, Norwich, Whitlingham

Service provided:
Transformer Installation

Scope of works:
  • Temporary Works Package
  • Electrical & Civil Design
  • HV Cable Works – Supply & Installation
  • LV Cable Works – Supply & Installation
  • Jointing & Terminations
  • Supply & Installation of Earthing
  • Civil Works
  • Supply & Installation of New Transformer
  • Testing and Commissioning

Download case study:

The Task

PTL were asked to provide sufficient resources and equipment to complete the supply and install of a temporary electrical solution to provide mains power to the sites existing MCC allowing removal of sites temporary generation. The temporary solution was required due to a large fire on site causing extensive damage

Works involved PTL performing several aspects of the design elements including, electrical, earthing and civil.

PTL excavated and backfilled all required HV and LV trenching and provided access to temporary TX location and existing LV Switch Room.

Both LV & HV cabling was installed followed by all relevant testing and commissioning, with all works being performed successfully as proven by the successful testing and reenergization.

Given time restraints safety and strategic planning was paramount, PTL ensured that works were completed as quickly as possible but to our same high standards.

Project Achievements

  • Worked closely Anglian Water to minimise operational risks & disruption
  • Efficient planning involving third parties
  • Careful planning and coordination to ensure shu tdowns and groundworks were kept to a minimum and manageable
  • Installations all carried out to manufacturers recommendation or better
  • Identification and mitigation of project risks
  • Successful provision of electrical solutions and associated assets
  • Ensured that all timescales and deadlines where me
View All Case Studies