Verne Data Centre, Keflavik

image
Client name:
Verne Data Centre, Keflavik

Location:
Verne Data Centre, Keflavik, Iceland

Service provided:
Preventative Maintenance & Testing on LV & HV Switchgear Systems

Scope of works:
  • LV Switchgear Maintenance
  • HV Switchgear Maintenance
  • Zero Disruption to Customer Base
  • Tight coordination
  • Phased isolation
  • Great teamwork across countries

Download case study:

The Task

Power Testing sent a team comprised of four technicians and two engineers to Iceland for two weeks to carry out testing, preventative maintenance and inspections on the switchgear systems.

Whilst we handled the testing, all switching duties were carried out by Verne Global’s engineering team, supported by a member of their UK team.

Key steps included:
Verne Global safely isolating and re-energising parts of the system in a phased approach.
• Power Testing conducting inspections and tests once it was safe to do so.
• Coordinating with Verne’s customer team to keep data clients informed.
• Holding daily meetings between teams to plan and adjust the work schedule.

The job relied on close communication and clearly defined responsibilities between both teams.

This joint effort highlighted what’s possible when two experienced teams work together with a shared goal. Thanks to detailed planning and open communication, Power Testing and Verne Global completed a complex job without impacting live operations, a true success in collaborative engineering.

Maintenance Achievements

  • All switchgear systems were successfully tested and inspected.
  • No downtime or service interruptions were reported by customers.
  • The partnership ran smoothly with clear communication throughout.
  • The process has laid the groundwork for future maintenance planning.

 

Quote from Vernes Senior Technical Operations Manager

“Power Testing demonstrated exceptional professionalism and technical competence during the inspection of our power distribution panels. Their thorough approach, attention to detail, and commitment to quality ensured the work was completed to the highest standard, reinforcing confidence in the reliability and safety of our systems.”

View All Case Studies